新華社廣州2月20日電(記者吳濤)廣東省惠州市(shi)龍(long)門縣龍(long)潭(tan)鎮(zhen)土湖村的龍(long)門換流(liu)(liu)站(zhan)工(gong)程現場,近百名施(shi)工(gong)人(ren)員(yuan)正在(zai)忙碌工(gong)作(zuo)。“站(zhan)內3個工(gong)作(zuo)面(mian)都同時(shi)復工(gong)了,包(bao)括柔性直流(liu)(liu)換流(liu)(liu)變熱流(liu)(liu)循環、閥廳設備(bei)吊裝、GIS設備(bei)安裝。”南(nan)方電網龍(long)門換流(liu)(liu)站(zhan)現場負責人(ren)朱云峰說。
龍門換流(liu)站是烏東德電(dian)站送電(dian)廣東廣西(xi)特(te)高壓多端直流(liu)示范工(gong)(gong)程(cheng)(以下簡稱“昆柳龍直流(liu)工(gong)(gong)程(cheng)”)在廣東的(de)落(luo)點。據南方電(dian)網公司(si)介紹,昆柳龍直流(liu)工(gong)(gong)程(cheng)7個作業(ye)點都已全面復工(gong)(gong),工(gong)(gong)程(cheng)背后的(de)科(ke)技攻關也在同步緊張推進(jin)。
昆(kun)柳龍直(zhi)流工(gong)(gong)程是我(wo)國(guo)《能(neng)源發(fa)展“十三五(wu)”規(gui)劃(hua)》及《電(dian)力發(fa)展“十三五(wu)”規(gui)劃(hua)》明(ming)確的(de)跨省區輸(shu)電(dian)重點工(gong)(gong)程,建(jian)成(cheng)后將(jiang)成(cheng)為首(shou)個特高(gao)壓(ya)多端混合直(zhi)流工(gong)(gong)程。按照計(ji)劃(hua),工(gong)(gong)程將(jiang)在明(ming)年全部建(jian)成(cheng)投產,屆時將(jiang)增(zeng)加800萬千瓦的(de)通道送(song)電(dian)能(neng)力,向粵港澳大(da)灣區和廣西輸(shu)送(song)云南清(qing)潔水電(dian)。目(mu)前(qian)工(gong)(gong)程總體已完成(cheng)80%,已進入(ru)沖(chong)刺階段(duan)。
朱云峰說(shuo),為落實工(gong)(gong)(gong)程防疫(yi)(yi)措施,龍門(men)換流站做(zuo)了(le)詳(xiang)細的復工(gong)(gong)(gong)方案,包含進(jin)場(chang)工(gong)(gong)(gong)人數量、來(lai)源地、春(chun)節(jie)期間動向(xiang)、身體狀況、防疫(yi)(yi)措施及(ji)物品(pin)配置(zhi)等內容(rong)。廠(chang)家運輸設備進(jin)場(chang)時,實行外來(lai)司機與(yu)站內人員“零(ling)接觸”傳遞。后續(xu)返工(gong)(gong)(gong)進(jin)場(chang)人員將按照(zhao)政府(fu)要求在指(zhi)定酒店先隔離14天(tian)再復工(gong)(gong)(gong)。現場(chang)施工(gong)(gong)(gong)人員每天(tian)測體溫(wen)3次,實行分批、分區域的分餐制。
工程承建(jian)單(dan)位(wei)南方電網超高(gao)壓(ya)公司基建(jian)部負(fu)責人表示,為確保(bao)昆(kun)柳龍直(zhi)流工程的建(jian)設進度,公司將加(jia)大物資供應協調力度,提前做(zuo)好復工后人員、機具、材料、工序(xu)等工作(zuo)安排(pai),對(dui)關鍵(jian)施工、關鍵(jian)路(lu)徑加(jia)大資源投入。